Sohan, Tarun and Umesh can each finish a carpentry job on their own in 16, 24 and 48 days respectively. All three start together, but at the end of the fourth day the quickest of them is called away to another site. How many further days do the other two need?

Competition practiceTime & Work / Pipes
  • A4 days
  • B8 days
  • C12 days
  • D24 days

Step-by-Step Solution

Take the job as 48 units: Sohan 3/day, Tarun 2/day, Umesh 1/day, so all three give 6 units a day. Four days put in 24 units, leaving 24. Sohan is the quickest and leaves, so Tarun and Umesh carry on at 2 + 1 = 3 units a day: 24 ÷ 3 = 8 more days. 4 days is what would remain if all three stayed (48 ÷ 6 = 8 days in all). 12 days leaves Tarun to finish alone (24 ÷ 2), forgetting Umesh. 24 days leaves Umesh alone (24 ÷ 1), forgetting Tarun.
Answer: B) 8 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A contractor promised to hand over a job on the 30th day and put 20 equally skilled…Cable-laying teams X and Y together can lay a stretch in 9 days; teams Y and Z together…A set of records was to be keyed in by a certain number of clerks in 12 days. Had 4 more…In a day 2 men do as much work as 3 women, and 3 women do as much as 5 children. If 4…Two taps fill a storage drum in 36 minutes and 45 minutes respectively when each works…