A job was planned for 30 workers in 25 days. After 10 days, 5 workers left. How many days late was the job finished?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A5 days
  • B2 days
  • C3 days
  • D18 days

Step-by-Step Solution

Left: worker-days for 25 workers = 18 days, planned 15. Late by 3 days.
Answer: C) 3 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A worker is promised Rs 7,200 and a watch for 12 months of work. He leaves after 7…A and B can finish a job in 36 days. A works twice as fast as B. If B leaves after 12…Working together, A and B do a job in 12 days. A works alone for 6 days, then B joins…Anita and Babli sew uniforms for a school. Anita alone would take 15 days and Babli 10…Kiran and Lata whitewash a boundary wall. The bar shows the wall in equal parts: Kiran…