A printing order is measured as 5,400 impression-units. Machine P turns out 45 units an hour, machine Q 30 units an hour and machine R 15 units an hour. P and Q run together for the first 24 hours, after which Q is withdrawn for servicing and R takes its place. How many hours does the whole order take?

Competition practiceTime & Work / Pipes
  • A84 hours
  • B60 hours
  • C72 hours
  • D90 hours

Step-by-Step Solution

P and Q together produce 75 units an hour, so 24 hours give 1,800 units and 3,600 remain. P and R together produce 60 units an hour, needing 3,600 ÷ 60 = 60 hours. Total 24 + 60 = 84 hours. 60 hours quotes only the closing stretch. 72 hours runs the whole 5,400 units at the opening pair's 75 an hour. 90 hours runs the whole order at the closing pair's 60 an hour, ignoring the faster opening 24 hours.
Answer: A) 84 hours

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

Sohan, Tarun and Umesh can each finish a carpentry job on their own in 16, 24 and 48…A contractor promised to hand over a job on the 30th day and put 20 equally skilled…Cable-laying teams X and Y together can lay a stretch in 9 days; teams Y and Z together…A set of records was to be keyed in by a certain number of clerks in 12 days. Had 4 more…In a day 2 men do as much work as 3 women, and 3 women do as much as 5 children. If 4…