A and B can do a job in 18 days and 24 days. They work together, but B leaves 3 days before the end. How many days does the job take?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A12 days
  • B11 4/7 days
  • C10 2/7 days
  • D13 days

Step-by-Step Solution

A works days, B works . Multiply by 72: , so .
Answer: B) 11 4/7 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A job was planned for 30 workers in 25 days. After 10 days, 5 workers left. How many…A worker is promised Rs 7,200 and a watch for 12 months of work. He leaves after 7…A and B can finish a job in 36 days. A works twice as fast as B. If B leaves after 12…Working together, A and B do a job in 12 days. A works alone for 6 days, then B joins…Anita and Babli sew uniforms for a school. Anita alone would take 15 days and Babli 10…