A can finish a job in 12 days and B in 15 days. They start together, but A leaves after 3 days. How long does B take to finish the rest?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A8 1/4 days
  • B9 days
  • C12 days
  • D6 3/4 days

Step-by-Step Solution

3 days together: . Left at days.
Answer: A) 8 1/4 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A daily-wage worker is paid Rs 500 for each day he works and fined Rs 100 for each day…A can do a job in 40 days. He works for 8 days, then B finishes it in 16 days. How long…A job must be done in 12 days. A alone takes 20 days. How many days must B (who takes 30…A can finish a job in 10 days, B in 12 days, C in 15 days. A and B start; C replaces A…A and B can do a job in 18 days and 24 days. They work together, but B leaves 3 days…