A job must be done in 12 days. A alone takes 20 days. How many days must B (who takes 30 days alone) work alongside A to finish in time?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A6 days
  • B8 days
  • C10 days
  • D12 days

Step-by-Step Solution

A in 12 days does . B must do days, the whole period.
Answer: D) 12 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A can finish a job in 10 days, B in 12 days, C in 15 days. A and B start; C replaces A…A and B can do a job in 18 days and 24 days. They work together, but B leaves 3 days…A job was planned for 30 workers in 25 days. After 10 days, 5 workers left. How many…A worker is promised Rs 7,200 and a watch for 12 months of work. He leaves after 7…A and B can finish a job in 36 days. A works twice as fast as B. If B leaves after 12…