A contractor promises a job in 30 days and hires 20 workers. After 15 days, only 40% is done. How many more workers must he hire to finish on time?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A10 workers
  • B30 workers
  • C5 workers
  • D15 workers

Step-by-Step Solution

40% took 300 worker-days, so the job is 750. Left 450 in 15 days needs 30 workers; hire 10 more.
Answer: A) 10 workers

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A takes 8 days and B 12 days for a job. With C's help they finish it in 3 days and are…A and B start a job together. A can do it in 24 days and B in 16 days. After 6 days, C…A group of 10 workers is to finish a job in 20 days. After 8 days, 5 more join. How many…A can finish a job in 12 days and B in 15 days. They start together, but A leaves after…A daily-wage worker is paid Rs 500 for each day he works and fined Rs 100 for each day…