A group of 10 workers is to finish a job in 20 days. After 8 days, 5 more join. How many days earlier than planned does the job finish?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A6 days
  • B8 days
  • C2 days
  • D4 days

Step-by-Step Solution

Left: worker-days for 15 workers = 8 days (not 12). Earlier by 4 days.
Answer: D) 4 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

A can finish a job in 12 days and B in 15 days. They start together, but A leaves after…A daily-wage worker is paid Rs 500 for each day he works and fined Rs 100 for each day…A can do a job in 40 days. He works for 8 days, then B finishes it in 16 days. How long…A job must be done in 12 days. A alone takes 20 days. How many days must B (who takes 30…A can finish a job in 10 days, B in 12 days, C in 15 days. A and B start; C replaces A…